| Table 1.16 Major Equipment Projects |
This table shows the MOD's major equipment projects as at 31 March 2008. It details the 20 largest projects on which the main investment decision has been taken (post Main-Gate) and the 10 largest projects yet to reach that point (pre Main-Gate). The information is taken from the Major Projects Report, relating to 31 March 2008, which provides a summary of each project's current status and progress to date.
Costs are on a resource basis at outturn prices. Forecast costs include accruals, VAT (less recoverable elements), resource elements such as interest on capital and inflation factors. Major Project Report costs relating to the pre-Main Gate projects are costs of the Assessment phase only. For post Main-Gate projects, costs are of the Demonstration and Manufacture phases.
The following diagram shows the CADMID cycle which is the basis for MOD Smart Procurement. The main investment decision is taken at Main-Gate, ie post assessment phase with the aim of ensuring that there is a high level of confidence in achieving time, cost and performance targets. Further information is contained in the Major Projects report.
|

|
| As at 31 March 2008 |
MPR2008 |
Post Main Gate Major Equipment Projects (Projects in Demonstration and Manufacture Phase only) |
In-Service date Forecast or Actual |
Financial Years of Peak Expenditure1 |
Forecast Cost (£ million) |
Change in Cost (£ million) from MPR2007 |
A400M |
2011 |
2010 & 2011 |
2 632 |
3 |
Advanced Jet Trainer2 |
2009 |
2007 & 2008 |
467 |
- |
Astute Class Submarine |
2009 |
2001 & 2005 |
3 806 |
8 |
Beyond Visual Range Air-To-Air Missile (BVRAAM)3 |
2013 & 2015 |
2010 & 2012 |
1 279 |
111 |
Falcon |
2010 |
2008 & 2011 |
291 |
-1 |
Future Joint Combat Aircraft (JCA)4 |
.. |
2005 & 2007 |
1 834 |
- 24 |
Future Lynx2 |
2014 |
2010 & 2011 |
1 911 |
- |
Merlin Mk 1 Capability Sustainment Programme |
2014 |
2009 & 2010 |
832 |
- |
Modernised Target Acquistion Designation Sight/Pilots Night Vision Sensor2 |
2009 |
2008 & 2009 |
228 |
- |
Naval Extremely High Frequency/Super High Frequency Satellite Communications Terminals2 |
2012 |
2008 & 2011 |
200 |
- |
Next Generation Anti-Armour Weapon (NLAW) |
2009 |
2006 & 2007 |
310 |
- 8 |
Nimrod Maritime Reconnaissance and Attack Mk4 |
2010 |
2002 & 2004 |
3 602 |
102 |
Soothsayer |
2009 |
2005 & 2010 |
202 |
7 |
Sting Ray Lightweight Torpedo Life Extension and Capability Upgrade |
2006 |
2007 & 2008 |
576 |
- 1 |
Support Vehicle |
2008 |
2009 & 2010 |
1 272 |
9 |
Terrier |
2011 |
2008 & 2009 |
313 |
14 |
Type 45 Destroyer |
2010 |
2003 & 2004 |
6 464 |
- |
Typhoon5 |
2003 |
2005 & 2006 |
* |
* |
Typhoon Future Capability Programme2 |
2012 |
2008 & 2009 |
436 |
- |
Watchkeeper |
2010 |
2009 & 2010 |
898 |
-3 |
| |
| As at 31 March 2008 |
|
|
| |
MPR 2008 |
Pre Main Gate Major Equipment Projects (Projects in Assessment Phase only) |
Forecast Cost (£ million) |
Eagle |
4 |
Future Aircraft Carrier (CVF) |
297 |
Future Integrated Soldier Technology (FIST) |
142 |
Future Rapid Effects System |
319 |
Future Strategic Tanker Aircraft (FSTA) |
38 |
Indirect Fire Precision Attack (IFPA) |
212 |
Maritime, Airborne, Surveillance, and Control (MASC) |
7 |
Military Afloat Reach & Sustainability (MARS)5 |
* |
Search and rescue - Helicopter (SAR-H) |
11 |
UK Military Flying Training System (UKMFTS) - Holistic |
32 |
| Source: Defence Equipment & Support |
| 1. Financial Year commencing 1 April - not necessarily concurrent years. |
| 2. Cost comparison not possible as project did not appear in previous MPR. |
| 3. In Service Date (ISD) redefined in MPR 2008 to reflect two-stage approach to delivering the capability |
| 4. The tailored Demonstration Main Gate noted but did not approve ISD. |
| 5. Cost data excluded on grounds of commercial sensitivity. |