| Table 1.17 Major Equipment Projects |
This table shows the MOD's major equipment projects as at 31 March 2007. It details the 20 largest projects on which the main investment decision has been taken (post Main-Gate) and the 10 largest projects yet to reach that point (pre Main-Gate). The information is taken from the Major Projects Report, relating to 31 March 2007, which provides a summary of each project's current status and progress to date. The Major Projects Report was changed in MPR2007 to remove forecast In Service Dates to reflect the Department's policy on public release of Assessment Phase project information.
Costs are on a resource basis at outturn prices. Forecast costs include accruals, VAT (less recoverable elements), resource elements such as interest on capital and inflation factors. Pre 1999 figures have been uplifted to 99/00 prices. Major Project Report costs relating to the pre-Main Gate projects are costs of the Assessment phase only. For post Main-Gate projects, costs are of the Demonstration and Manufacture phases.
|
| The following diagram shows the CADMID cycle which is the basis for MOD Smart Procurement. The main investment decision is taken at Main-Gate, ie post assessment phase with the aim of ensuring that there is a high level of confidence in achieving time, cost and performance targets. Further information is contained in the Major Projects report. |
| |
 |
| |
| As at 31 March 2007 |
MPR2007 |
Post Main Gate Major Equipment Projects (Projects in Demonstration and Manufacture Phase only) |
In-Service date Forecast or Actual |
Financial Years of Peak Expenditure1 |
Forecast Cost (£ million) |
Change in Cost (£Million) from MPR2006 |
A400M |
2011 |
2009 & 2010 |
2 629 |
13 |
|
Astute Class Submarine |
2008 |
2001 & 2005 |
3 798 |
142 |
|
Beyond Visual Range Air-To-Air Missile (BVRAAM) |
2013 |
2009 & 2012 |
1 168 |
-36 |
|
Bowman |
2004 |
2004 & 2005 |
2 009 |
-10 |
2 |
Brimstone |
2005 |
1999 & 2005 |
899 |
-1 |
|
C Vehicle Capability3 |
2006 |
2019 & 2020 |
703 |
- |
|
Falcon4 |
2010 |
2008 & 2011 |
292 |
- |
|
Guided Multiple Launch Rocket System |
2007 |
2006 & 2010 |
91 |
-172 |
|
Joint Combat Aircraft (JCA)5 |
.. |
2005 & 2007 |
1 858 |
-58 |
|
Merlin Mk 1 Capability Sustainment Programme4 |
2014 |
2009 & 2010 |
832 |
- |
|
Next Generation Anti-Armour Weapon (NLAW) |
2008 |
2007 & 2008 |
318 |
4 |
|
Nimrod Maritime Reconnaissance and Attack Mk4 |
2010 |
2002 & 2004 |
3 500 |
-16 |
|
Precision Guided Bomb (PGB) |
2007 |
2006 & 2007 |
277 |
-67 |
2 |
Soothsayer4 |
2008 |
2007 & 2010 |
195 |
- |
|
Sting Ray Lightweight Torpedo Life Extension and Capability Upgrade |
2006 |
2007 & 2008 |
577 |
-12 |
2 |
Support Vehicle |
2008 |
2009 & 2010 |
1 263 |
-75 |
|
Terrier |
2009 |
2008 & 2009 |
299 |
3 |
|
Type 45 Destroyer |
2010 |
2003 & 2004 |
6 464 |
354 |
|
Typhoon6 |
2003 |
2006 & 2008 |
* |
* |
|
Watchkeeper4 |
2010 |
2009 & 2010 |
901 |
- |
|
| Source: Defence Equipment & Support |
As at 31 March 2007 |
MPR 2007 |
|
Pre Main Gate Major Equipment Projects (Projects in Assessment Phase only) |
Forecast Cost (£ million) |
Future Aircraft Carrier (CVF) |
299 |
Future Integrated Soldier Technology (FIST) |
36 |
Future Rapid Effects System |
618 |
Future Strategic Tanker Aircraft (FSTA) |
37 |
Indirect Fire Precision Attack (IFPA) |
67 |
Maritime, Airborne, Surveillance, and Control (MASC) |
7 |
Military Afloat Reach & Sustainability (MARS)5 |
* |
Search and rescue - Helicopter (SAR-H) |
12 |
UKCEC Frigate and Destroyer Programme |
55 |
UK Military Flying Training System (UKMFTS) - Holistic |
30 |
| Source: Defence Equipment & Support |
| 1. Financial Year commencing 1 April - not necessarily concurrent years. |
| 2. Forecast figures in MPR 2006 were revised after the publication of UKDS 07. When comparing published UKDS 07 forecast and latest MPR 2007 forecasts the differences will not align (See Pages 30, 106 and 118 of the Major Projects Report for further details). |
| 3. PFI Service with annual service payment. |
| 4. Cost comparison not possible as project did not appear in previous MPR. |
| 5. The tailored Demonstration Main Gate noted but did not approve In Service Date (ISD). |
| 6. Cost data excluded on grounds of commercial sensitivity. |